Sr. No.
|
Description
|
20 feet
(In Rs.)
|
40 feet
(In Rs.)
|
|
1
|
Cargo unloading from truck and stacking in warehouse, assisting cargo inspection
and stuffing to the allotted container.
A) On Wheel – Manual
B) On Wheel - Mechanical
( Crane or forklift if any will be extra on case to case basis)
|
3,100
4,100
|
4,600
6,300
|
|
2
|
Cargo unloading from truck and stacking in open yard, Empty Lift Off, assisting
cargo inspection and stuffing to the allotted container and Laden Lift on.
A) Ground Stuffing - Manual
B) Ground Stuffing - Mechanical
( Crane or Forklift if any will be extra on case to case basis
|
4,000
5,000
|
5,800
7,500
|
|
3
|
Granite stuffing
Cargo unloading from truck and stacking in open yard, empty lift off, assisting
cargo inspection and stuffing to the allotted container and laden lift on.
( Lashing charges are extra and as applicable)
|
5,500
|
|
|
4
|
On wheel / Ground Mechanical
Coco fibre / stuffing charges
Coconut coir -stuffing
|
|
7,500
|
|
5
|
Maize ( in 100 KG Bags and below )
Unloading from Truck, Stacking and Bulk Stuffing.
|
6,200
|
|
|
6
|
Chilli Stuffing
|
|
7,500
|
|
7
|
Rice Stuffing
|
4,500
|
|
|
8
|
Warehouse Storage Charges (Incl. First day of Arrival)
General Cargo :
1. First 3 days
2. 4th To 7th Day
3. 8th Day Onwards
|
Free
375
475
|
Free
700
850
|
|
9
|
Granite storage charges open yard
1. 1st To7th Day (Incl. First day of Arrival)
2. 8th To 15th Day
3. 16th Day Onwards
Open Yard Storage Charges : General Cargo Per Day
|
Free
300
500
Rs 15 per Sq.Mtr. or MT whichever is higher
|
Free
400
1000
|
|
10
|
Granite Slabs –Crates Storage Charges/Day (Part thereof)
|
Rs.10 per MT
|
|
11
|
Export Stuffed Container Storage Charges
|
|
1st Days Free
|
|
|
|
2nd To 3rd days
|
300
|
550
|
|
4th To 10th days
|
550
|
750
|
|
11th Days Onwards
|
1,000
|
2,000
|
|
12
|
Load Container Lift Off/Lift On Charges Per Operation
|
1,050
|
1,650
|
|
Empty Container Lift Off/Lift On Charges Per Operation
|
500
|
1,000
|
|
13
|
Empty Container Storage Charges
|
|
|
|
0 To 3rd days
|
Free
|
Free
|
|
4th To 10th days
|
75
|
125
|
|
11th To 20th days
|
125
|
250
|
|
21st To 30th days
|
250
|
350
|
|
30th days Onwards
|
350
|
700
|
|
14
|
Weighment charges : Per Container/Truck
|
250
|
250
|
|
15
|
Equipment hire charges (Min. 4 hours)
|
|
3 Ton FLT
|
Rs.1,500/- for 4 Hrs.
|
|
5 Ton FLT
|
Rs.3,500/- for 4 Hrs.
|
|
12 Ton & 16 Ton FLT
|
Rs.4,500/- for 4 Hrs.
|
|
10 Ton & 14 Ton Crane ( Escorts)
|
Rs.2,000/- for 4 Hrs.
|
|
40 Ton Crane
|
Rs.6,000/- for 4 Hrs.
|
|
16
|
i) Central Excise Container / Self Seal - On Wheel Inspection
|
750
|
1,500
|
|
ii) Central Excise Container / Self Seal - Ground Inspection
|
2,100
|
3,800
|
|
iii) Export On Wheel Inspection Charges - Self Seal
|
1,200
|
2,500
|
|
iv) Export Ground Inspection Charges - Self Seal
|
2,400
|
3,800
|
|
Central Excise Container /Self Seal Storage
|
|
1st Day Free
|
0
|
0
|
|
2nd to 3rd Day
|
300
|
550
|
|
4th to 10th
|
550
|
750
|
|
11th Day Onwards
|
1,000
|
2,000
|
|
Additional Charge
|
|
Sr. No
|
Description of Operations
|
20 feet
(In Rs.)
|
40 feet
(In Rs.)
|
|
1
|
Value Added Services
|
100
|
200
|
|
2
|
Seal charges
|
75
|
75
|
|
3
|
Fuel surcharges
|
1000
|
1500
|
|
4
|
Energy surcharge
|
650
|
650
|
|
5
|
Documentation charge
|
150
|
150
|
|
6
|
Shifting within CFS : Laden Containers
|
850
|
1,450
|
|
7
|
Examination-Second & subsequent Open Order ( for each operation)
|
1,025
|
1,525
|
|
8
|
Additional Charges for Polluting, Dusting & Fine Powder Cargo
|
1,000
|
2,000
|
|
9
|
Royalty Charges for Palletization work
|
600
|
1,200
|
|
10
|
For Heavy Cargo like Machines etc., and value added services, charges will be extra.
|
|
|
|
11
|
Rates are subject to change without prior intimation.
|
|
|
|
12
|
For Crane Handling & Additional Forklift Charges will be Extra.
|
|
|
|
13
|
ODC / Flat -Rack container Transportation charges on case to case basis.
|
|
|
|
14
|
Double the normal Tariff for Handling & Storage of ODC, Flat-rack and Open-Top
containers.
|
|
|
|
15
|
45' Container Storage/ Handling: 25% Extra on 40' Feet Charges.
|
|
|
|
16
|
Hazardous container Handling and Storage charges 125% of DC Containers Rate.
|
|
|
|
17
|
Loading/Unloading Cargo into lorry per Operation Rs.360/Per Truck
|
|
|
|
18
|
Preventive Escort charges for OOG/ODC/FR/OT/Hazardous containers will be extra.
|
|
|
|
19
|
Extra Charges applicable for Coconut Fiber/Pith/Cotton Bales/Heavy Cargos likes
Machines etc. Value added services cargo.
|
|
|
|
Conditions
|
|
Sr. No
|
Description of Operations
|
|
1
|
Local Transport, Additional Handling shall be charged Extra.
|
|
2
|
The above rates are subject to the following condition : In case any increase in
fuel, spare parts, tyres,
|
|
Insurance and TOA rates, our rates will be increased on Pro rata basis as per industrial
norms.
|
|
3
|
Rates subject to change without prior intimation.
|
|
4
|
The rates quoted above are considering normal de-stuffing only (using forklift).
Any odd shape/heavy Items cargoes/ Open top containers which require additional
handling equipment like crane etc. will be charged extra.
|
|
5
|
Addition charges will be levied for cargo requiring special services like dun age,
lashing, materials etc.
|
|
6
|
Shipping Line / CHA will be requiring paying Customs Overtime, if any required work
done at CFS.
|
|
7
|
PD Accounts system is availed for the clients for ease of transactions.
|
|
8
|
Against possible risk during transportation & storage & the company assumes
no liability in this respect. In case if the insurance is not covered by consignee/shipper
they have inform us in advance by us for which charges will be recover from consignee
/ shipper.
|
|
9
|
Prior to gate out of Cargo/Container, all CFS dues should be paid.
|
|
10
|
Service Tax & other government levies shall be applicable at the prevailing
rates at the time of Billing.
|
|
11
|
Container handled with slings will be considered as OOG.
|
|
12
|
Volume discount will be given based on the Turnover.
|
|
13
|
All charges are in Indian Rupees ( INR)
|
|
14
|
Service Tax and other statutory charges as applicable will be extra.
|